ROMO HQ 2019 Update
ROMO HQ PROJECT
We have been engaged on this contract since October 2017 providing all aspects of groundworks.
Works carried out on this project include:
· 250 foundation pads and holding down bolts
· Ground beams
· CBR and Cube Testing
· 3500m3 of concrete works
· 2000m of 90mm and 32mm water supplies
· 6500m of ducting
· Internal and external concrete slabs
· 6000m3 of muck away
· Grouting of steel columns
· Storm and foul drainage
· 600m of Gatic/Aco channel drain
· 2600m of kerbing
· Lighting column bases
· 2000m3 of 6f2 laid
· 5000m3 of type one laid
· 175m long Gabion wall
· External paving
· 500m3 of bedrock excavation
· Shuttering works
· 300m of concrete upstands
· 120m of precast concrete cable troughs installed
· Substation bases for new incoming HV supplies including GRP housing supplied