ROMO HQ 2020 Update

After two and a half years and over £2.5 million of work carried out on this project it is finally coming to an end. We are currently finishing shaping up the landscape areas, installing footpaths and spreading topsoil over 12,500m2.

ROMO Sutton Ashfield 3 Point Construction

ROMO HQ 2019 Update

ROMO HQ PROJECT

We have been engaged on this contract since October 2017 providing all aspects of groundworks.

Works carried out on this project include:

· 250 foundation pads and holding down bolts

· Ground beams

· CBR and Cube Testing

· 3500m3 of concrete works

· 2000m of 90mm and 32mm water supplies

· 6500m of ducting

· Internal and external concrete slabs

· 6000m3 of muck away

· Grouting of steel columns

· Storm and foul drainage

· 600m of Gatic/Aco channel drain

· 2600m of kerbing

· Lighting column bases

· 2000m3 of 6f2 laid

· 5000m3 of type one laid

· 175m long Gabion wall

· External paving

· 500m3 of bedrock excavation

· Shuttering works

· 300m of concrete upstands

· 120m of precast concrete cable troughs installed

· Substation bases for new incoming HV supplies including GRP housing supplied

Racecourse Retail Construction

Racecourse Retail Park – Aintree

This project involved redeveloping an existing retail unit to make way for a new Next store. Works carried out on this unit include but not limited to:

Break out 144 holes in the floor slab for piling, pile caps, lift pit full construction, escalator pit, de-watering, underpinning, floor slab extension, glazing foundations, steel fixing, shuttering, block paving, ground level changes, kerbs, asphalt, drainage connections, demolition works, joinery works, foul drainage, pop-ups, manholes, street furniture.

Pier Point Retail Park Construction Car Park

Pierpoint Retail Park – Kings Lynn

This project consisted of the transformation of four existing retail units into new stores for Next, Tapi, DFS and B&M along with the resurfacing of the car park. Works carried out on this project include but not limited to:

Concrete floor slab extension, ACO slot drains, gulley pots, PCC chambers, metered water supplies, BT ducts, electric ducts, draw pits, new kerb lines, concrete ramps, retaining walls, ground level changes, brickwork, manholes, storm and foul pipes, pop-ups, footpaths, block paving, bollards, stop blocks, fencing, kee-klamp, sub-station bases, knee-rail fencing, trolley bays, class M handrails, metal work painting, car park resurfacing, white lining, palisade fencing, Armco barrier, street furniture, methane vent pipes, lift pit infill, blockwork repair, channels, full construction tarmac, cycle hoops, speed bumps, topsoil, concrete slabs, formwork, paving slabs, concrete foundations, hard-standings

Festival Retail Park Slabbing

Festival Retail Park – Hanley, Stoke-On-Trent

The project comprised of demolishing a Toys’R’Us back to shell and dividing the unit into a new store for both Next and River Island. Works carried out during the project include but are not limited to:

Core drilling 100 holes into the floor slab for piling to enable a mezzanine floor to be installed, pile caps, double lift pit, single lift pit, double escalator pit, 360m2 concrete floor slab extension, cube testing, shuttering, steel fixing, bolt boxes, demolition, piling mats, ventform, methane vent system, ground beams, paving, new kerb lines, full construction tarmac, white lining, bollards, new storm drainage system, new foul system, street furniture.