Engaged on this site since September 2019 we are currently carrying out a range of civils works including in-situ concrete, pile caps, forming openings through existing concrete, suspended slabs, mezzanine decks, walls, tables and pits. 5m deep tank for cess pit, oil interceptor tank, 26m x 8m attenuation tank, all new foul and storm drainage site wide, ducting and new services. 900m2 of various external concrete slabs. 500t crane mat and plate load testing. We are also carrying out the brick and blockwork package which entails a 11m high by 12m long extension to the building. As our works near completion in June we will move on to external works of groundworks kerbing, landscaping, footpaths, grass block and 1000m2 of tarmac.
ROMO HQ 2019 Update
ROMO HQ PROJECT
We have been engaged on this contract since October 2017 providing all aspects of groundworks.
Works carried out on this project include:
· 250 foundation pads and holding down bolts
· Ground beams
· CBR and Cube Testing
· 3500m3 of concrete works
· 2000m of 90mm and 32mm water supplies
· 6500m of ducting
· Internal and external concrete slabs
· 6000m3 of muck away
· Grouting of steel columns
· Storm and foul drainage
· 600m of Gatic/Aco channel drain
· 2600m of kerbing
· Lighting column bases
· 2000m3 of 6f2 laid
· 5000m3 of type one laid
· 175m long Gabion wall
· External paving
· 500m3 of bedrock excavation
· Shuttering works
· 300m of concrete upstands
· 120m of precast concrete cable troughs installed
· Substation bases for new incoming HV supplies including GRP housing supplied
Pierpoint Retail Park – Kings Lynn
This project consisted of the transformation of four existing retail units into new stores for Next, Tapi, DFS and B&M along with the resurfacing of the car park. Works carried out on this project include but not limited to:
Concrete floor slab extension, ACO slot drains, gulley pots, PCC chambers, metered water supplies, BT ducts, electric ducts, draw pits, new kerb lines, concrete ramps, retaining walls, ground level changes, brickwork, manholes, storm and foul pipes, pop-ups, footpaths, block paving, bollards, stop blocks, fencing, kee-klamp, sub-station bases, knee-rail fencing, trolley bays, class M handrails, metal work painting, car park resurfacing, white lining, palisade fencing, Armco barrier, street furniture, methane vent pipes, lift pit infill, blockwork repair, channels, full construction tarmac, cycle hoops, speed bumps, topsoil, concrete slabs, formwork, paving slabs, concrete foundations, hard-standings
Romo HQ – Sutton-In-Ashfield
We are currently engaged on this contract to provide 250 foundation pads and bolt boxes for the new warehouse. This involves excavating down to bedrock some 4m in places, filling with concrete and inserting holding down bolts for the steel columns to sit on. We have currently laid around 2900 cubic meters of concrete. Works also undertaken include:
90mm mains and 32mm water supply install including manholes, control valves and check valve, 5500 tonnes of excavation and muck shift, grouting, temporary drainage, ground beams, shuttering, blockwork, substation concrete base, CBR testing, cube testing, concrete slabs, ducting to lower existing HV and street lighting cable, full construction entrance road, fencing, CCTV drainage survey.